Science North struggling with $10M in cost overruns, poor planning, auditor says
Poor planning and project management led to a $10 million increase in Science North’s Go Deeper project, Ontario’s acting auditor general says.
Nick Stavropoulos said Wednesday in his report that even with reduced scope, the now-$15 million project is still coming in far over-budget. Initially expected to open this year, Go Deeper won’t open until sometime in 2024.
“We found that the cost overrun and delay were caused by poor planning and ineffective project management,” Stavropoulos wrote.
“For example, no reliable third-party estimate was completed during the planning phase to assess the reasonableness of the cost projections. A more reliable cost estimate would have been produced if a consultant with an engineering and construction background had been engaged during the planning phase.”
While pointing the finger at the planning process, he said the budget increases were largely due to rising excavation and construction costs.
“The project had also run into significant delays,” Stavropoulos wrote.
“In 2019 Science North proceeded with the project, setting an initial completion date of February 2023. At the time of our audit, the project was expected to be completed by winter 2024. The delay was mostly due to the COVID-19 pandemic, the City of Greater Sudbury identifying additional requirements for site remediation, which delayed municipal permit approvals, and a lack of available funding.”
Currently, Science North has paused "key elements of the project," the report said, because of a lack of funds and are again reviewing it to reduce the scope and cut costs further.
Poor planning and project management led to a $10 million increase in Science North’s Go Deeper project, Ontario’s acting auditor general says. (File)
In addition, the centre’s plan to expand to Thunder Bay and Kenora is estimated to cost more than $90 million, but a cost-benefit analysis hasn’t been completed.
“Science North sought board approval for this expansion without the benefit of a business case that would include a cost/benefit analysis and assessment of alternative options,” the report said.
“At the time of our audit, Science North had received only conditional board support for the expansion and had not yet sought funding for the expansion from any level of government or from the private sector.”
Science North estimates that operating budgets for the two new science centres would be $5.5 million and asked the province to cover $4 million.
“Centre management projected that self-generated revenue would cover the remaining $1.5 million,” the report said.
“The ministry had not assessed the feasibility and financial sustainability of the expansion to Thunder Bay and Kenora.”
IMAX ATTENDANCE PLUNGED
Attendance before the COVID-19 pandemic was down by eight per cent, driven largely by plunging attendance at the IMAX theatre, which had declined by 26 per cent from 2015-2019.
But it’s not all bad news: attendance has recovered since the pandemic ended.
“In 2022/23, attendance has increased by three per cent from pre-pandemic levels,” the report said.
“Science North projected attendance to remain at this level in the upcoming three fiscal years.”
The average age of exhibits both at Science North and Dynamic Earth is 11 years and none have changed significantly since 2017.
The report also recommended the centre change its accounting practices so costs are allocated to specific lines of business.
“Without allocating these costs, it is difficult to assess which lines of business are profitable and which need to manage costs more effectively,” the report said.
In its response to the AG report, Science North said it agrees with the recommendations.
- Download our app to get local alerts on your device
- Get the latest local updates right to your inbox
“In leveraging new technology, Science North will improve its current process for allocating appropriate costs to lines of business where able and will continue to seek and analyze new opportunities for self-generated revenue,” the centre said in its response.
“The organization will take additional measures to ensure visitor feedback informs all major exhibits and their renewals, while further leveraging memberships with Canadian and international science centre associations to streamline research and best practices.”
Read the full report, and Science North’s responses, here.
CTVNews.ca Top Stories
![](https://www.ctvnews.ca/polopoly_fs/1.6972910.1721665918!/httpImage/image.jpg_gen/derivatives/landscape_800/image.jpg)
Harris praises Biden's 'unmatched' legacy, claims many of the delegates she needs for the nomination
U.S. Vice President Kamala Harris moved swiftly Monday to lock up Democratic delegates behind her campaign for the White House after President Joe Biden stepped aside amid concerns from within their party that he would be unable to defeat Republican Donald Trump.
WATCH LIVE 'We failed,' says Secret Service director grilled on Trump assassination attempt
Secret Service Director Kimberly Cheatle said Monday that her agency failed in its mission to protect former U.S.President Donald Trump during a highly contentious congressional hearing with lawmakers of both major political parties demanding she resign over security failures that allowed a gunman to scale a roof and open fire at a campaign rally.
Hollywood reacts to Joe Biden exiting the U.S. presidential race
Hollywood was quick to react to the news that U.S. President Joe Biden was ending his bid for re-election and endorsing Vice President Kamala Harris.
Prince George is 11 -- see his birthday photo
Prince George has turned 11, and as per tradition his proud parents have released an official portrait to mark the occasion.
Two-thirds of Canadians polled say they 'desperately' need interest rates to go down
A new survey says the Bank of Canada's recent interest rate cut did little to change Canadians' negative perceptions about their personal finances.
Israel orders evacuation of part of Gaza humanitarian zone as war's toll passes 39,000 Palestinians
The Israeli military ordered the evacuation Monday of part of a crowded area in the Gaza Strip it had designated a humanitarian zone, saying it is planning an operation against Hamas militants there.
Wildfire forces evacuation of B.C.'s Barkerville gold rush heritage site
Visitors have been told to avoid B.C.'s historic Barkerville gold rush town, which is among several areas in the province's Cariboo region under evacuation orders due to the massive Antler Creek wildfire.
LeBron James to be Team USA's male flag bearer for Olympic Opening Ceremony
NBA legend LeBron James has been selected as Team USA’s male flag bearer for the Opening Ceremony of the Paris Olympic Games.
The pilot who died in crash after releasing skydivers near Niagara Falls has been identified
Officials on Sunday released the name of a pilot who died in a skydiving flight after her passengers jumped from the aircraft near the Niagara Falls.