Sudbury construction company, Ontario government embroiled in $20M lawsuit over Hwy. 69 widening
A Sudbury construction company is suing the Ontario government, arguing the contract it signed to expand part of Highway 69 incorrectly estimated the amount of rock that would be leftover at the end of the project.
The $20 million suit centres on whether the province incorrectly estimated the amount of rock, as Bot Construction claims, or whether the excess rock is a result of the way it was blasted, as the Ontario government claims.
Lawyers for the company argue the excess rock is a result of a design error, as well as errors estimating the extent to which crushed and broken rock takes up more volume than rock sitting in the bank.
Bot argues that its bid for the work was much lower than it should have been because of the errors. It said the amount of rock it had to deal with was "approximately 26 times more than was estimated."
"The plaintiffs’ position is that this case is fundamentally about whether two pieces of information provided by the defendant to bidders on the contract were incorrect and if so, was the price the plaintiffs’ bid for the contract artificially deflated by its reliance on that incorrect information," said a court transcript of the latest hearing on the case, released May 31.
In response, lawyers from the province said Bot is responsible for the excess rock because "of the way it conducted the work on the project."
"The defendant asserts that the source of the additional rock is the drilling and blasting techniques employed by the plaintiffs and its subcontractors," the transcript said.
"Specifically, one source of additional rock would be over-blasting by the plaintiffs: blasting beyond the design lines of the contract, also referred to as 'overbreak.' While over-blasting is permitted, disposal of any additional rock generated by over-blasting would be the responsibility of the plaintiffs."
The province argued that Bot should have to provide extensive documentation on their blasting techniques to determine whether that was the cause of the excess rock.
But Bot argued their case is based on arguments the information provided the province in the contract was incorrect, leading the company to bid too low. Specific blasting techniques, they argue, aren't relevant.
While largely finding for Bot, the judge in the case said the company had to say whether an expert report they had prepared would allow them to answer how much they would have bid on the contract at the time, if the alleged design errors had not been made.
"If the report did provide them with sufficient information/data to answer how they would have bid but for the design error, they must also answer that question," the judge ruled.
"If they do not have the data/ information to respond, they are not required to do so, because that would impose an undue burden of work."
Read the full transcript here.
CTVNews.ca Top Stories
BREAKING Alice Munro, Nobel literature winner revered as short story master, dead at 92
Nobel laureate Alice Munro, the Canadian literary giant who became one of the world's most esteemed contemporary authors and one of history's most honoured short story writers, has died at age 92.
Latest updates on air quality alerts, and when the smoke may reach Ontario and Quebec
Wildfires have led Environment Canada to issue air quality advisories for parts of B.C., Alberta, Manitoba, Saskatchewan and the Northwest Territories, as forecasters warn the smoke could drift farther east.
Are these Canada's best restaurants? Annual top 100 list revealed
The annual list of Canada's top restaurants in the country was just released and here are the places that made the 2024 cut.
Attack on prison van in France kills 2 officers, inmate escapes
Armed assailants killed two French prison officers and seriously wounded three others in an attack on a convoy in Normandy on Tuesday and an inmate escaped, officials said.
Maximum payout for LifeLabs class-action drops from $150 estimate to $7.86
Canadian LifeLabs customers who filed an application for a class-action settlement began receiving their payments this week, though at a much lower amount than initially expected.
Steal a car, lose your driver's licence for 10 years under new Ontario proposal
Repeat car thieves may face lengthy licence bans under proposed changes to Ontario’s Highway Traffic Act.
$1.6B parts plant for Honda electric vehicle batteries coming to Niagara Region
A Japanese company has announced it will build an approximately $1.6-billion plant in Ontario's Niagara Region that will make a key electric vehicle battery component as part of Honda's supply chain in the province.
B.C. brings in law on name changes on day that child killer's new identity revealed
The BC NDP have tabled legislation aimed at stopping people who have committed certain heinous acts from changing their names.
Manitoba premier to visit areas impacted by wildfire
Manitoba Premier Wab Kinew will get a close-up look at the devastation from a large wildfire burning in northern Manitoba Tuesday.