Science North struggling with $10M in cost overruns, poor planning, auditor says
Poor planning and project management led to a $10 million increase in Science North’s Go Deeper project, Ontario’s acting auditor general says.
Nick Stavropoulos said Wednesday in his report that even with reduced scope, the now-$15 million project is still coming in far over-budget. Initially expected to open this year, Go Deeper won’t open until sometime in 2024.
“We found that the cost overrun and delay were caused by poor planning and ineffective project management,” Stavropoulos wrote.
“For example, no reliable third-party estimate was completed during the planning phase to assess the reasonableness of the cost projections. A more reliable cost estimate would have been produced if a consultant with an engineering and construction background had been engaged during the planning phase.”
While pointing the finger at the planning process, he said the budget increases were largely due to rising excavation and construction costs.
“The project had also run into significant delays,” Stavropoulos wrote.
“In 2019 Science North proceeded with the project, setting an initial completion date of February 2023. At the time of our audit, the project was expected to be completed by winter 2024. The delay was mostly due to the COVID-19 pandemic, the City of Greater Sudbury identifying additional requirements for site remediation, which delayed municipal permit approvals, and a lack of available funding.”
Currently, Science North has paused "key elements of the project," the report said, because of a lack of funds and are again reviewing it to reduce the scope and cut costs further.
Poor planning and project management led to a $10 million increase in Science North’s Go Deeper project, Ontario’s acting auditor general says. (File)
In addition, the centre’s plan to expand to Thunder Bay and Kenora is estimated to cost more than $90 million, but a cost-benefit analysis hasn’t been completed.
“Science North sought board approval for this expansion without the benefit of a business case that would include a cost/benefit analysis and assessment of alternative options,” the report said.
“At the time of our audit, Science North had received only conditional board support for the expansion and had not yet sought funding for the expansion from any level of government or from the private sector.”
Science North estimates that operating budgets for the two new science centres would be $5.5 million and asked the province to cover $4 million.
“Centre management projected that self-generated revenue would cover the remaining $1.5 million,” the report said.
“The ministry had not assessed the feasibility and financial sustainability of the expansion to Thunder Bay and Kenora.”
IMAX ATTENDANCE PLUNGED
Attendance before the COVID-19 pandemic was down by eight per cent, driven largely by plunging attendance at the IMAX theatre, which had declined by 26 per cent from 2015-2019.
But it’s not all bad news: attendance has recovered since the pandemic ended.
“In 2022/23, attendance has increased by three per cent from pre-pandemic levels,” the report said.
“Science North projected attendance to remain at this level in the upcoming three fiscal years.”
The average age of exhibits both at Science North and Dynamic Earth is 11 years and none have changed significantly since 2017.
The report also recommended the centre change its accounting practices so costs are allocated to specific lines of business.
“Without allocating these costs, it is difficult to assess which lines of business are profitable and which need to manage costs more effectively,” the report said.
In its response to the AG report, Science North said it agrees with the recommendations.
- Download our app to get local alerts on your device
- Get the latest local updates right to your inbox
“In leveraging new technology, Science North will improve its current process for allocating appropriate costs to lines of business where able and will continue to seek and analyze new opportunities for self-generated revenue,” the centre said in its response.
“The organization will take additional measures to ensure visitor feedback informs all major exhibits and their renewals, while further leveraging memberships with Canadian and international science centre associations to streamline research and best practices.”
Read the full report, and Science North’s responses, here.
CTVNews.ca Top Stories
![](https://www.ctvnews.ca/polopoly_fs/1.6979388.1722030190!/httpImage/image.jpg_gen/derivatives/landscape_800/image.jpg)
BREAKING Celine Dion stages comeback with performance at Paris Olympics opening ceremony
Celine Dion staged the comeback of her career during the opening ceremony at the Olympic Games in Paris.
Jasper wildfire: 'Several weeks' before Jasper can return, premier says
Premier Danielle Smith said Friday afternoon in Hinton while weather conditions are cooler, the Jasper fire is still considered out of control and that Jasper residents can expect to be away from their homes "for several weeks."
Driver charged after flashing high beams at approaching police
Orillia OPP arrested and charged a driver with impaired driving after flashing their high beams.
'He was just gone': Police ramp up search for vulnerable 3-year-old boy in Mississauga, Ont.
Police in Mississauga are conducting a full-scale search of the city’s biggest park for a non-verbal toddler who went missing Thursday evening. Sgt. Jennifer Trimble told reporters Friday morning that there has been no trace of three-year-old Zaid Abdullah since 6:20 p.m., when he was last seen with his parents in Erindale Park, near Dundas Street West and Mississauga Road.
Irish museum pulls Sinead O'Connor waxwork after just one day due to backlash
An Irish museum will withdraw a waxwork of singer-songwriter Sinéad O’Connor just one day after installing it, following a backlash from her family and the public, it told CNN in a statement on Friday.
Turpel-Lafond won't sue CBC over Cree heritage report that took 'heavy toll': lawyer
The lawyer for a former judge whose claims to be Cree were questioned in a CBC investigation says his client is not considering legal action against the broadcaster after the Law Society of British Columbia this week backed her claims of Indigenous heritage.
Health Canada warns some naloxone kits contain false instructions
Health Canada is warning some take-home naloxone kits come with bad instructions that should be ignored in favour of the correct guidance.
Winnipeg senior's account overdrawn $146,000 for water bill
A Winnipeg senior is getting soaked with a six figure water bill.
Paris Olympics kicks off with ambitious but rainy opening ceremony on the Seine River
Celebrating its reputation as a cradle of revolution, Paris kicked off its first Summer Olympics in a century on Friday with a rain-soaked, rule-breaking opening ceremony studded with stars and fantasy along the Seine River.