First built more than a century ago as an Ontario National Railway station, public works manager Ken Krcel said the city hadn’t done any major renovations since purchasing the building in 2010.
He said several areas need improving and that it will be a more than $1.4 million project.
“It includes reclining the walls, new plumbing, new heating and any asbestos remediation that (workers) may come across,” Krcel said.
The terminal’s office space is limited, which the city feels can be fixed by adjusting the building’s layout and converting some storage rooms into offices.
Krcel also noted a safety issue with the terminal’s public washrooms. Their antiquated doors lock from the inside, which he said has lent itself to vandalism and mischief.
“People have gone in, locked themselves in there and basically vandalized the washrooms, wrecked them and left them in a state that the next person from the public going in, it’s unusable and they’re unsafe,” Krcel said.
“They’ll be designed without physical doors, just the bathroom stall doors. A series of corridors that would prevent us from losing access to the washrooms at any time.”
He said the renovations won’t affect the exterior of the building, which has largely remained in its original condition, with signs of expansions before the city took it over.
The chair of the municipal heritage committee, Nicola Alexander, said the terminal stands out as a reminder of the city’s past, when rail was the only way in and out of the area.
“Some of the heritage features of this building are the original face brick, these beautiful brackets that are holding up the eaves,” Alexander said.
“You can still see the original foundation stone, with the carving commemorating the opening of this building in 1916.”
The interior renovations will be paid for with funding from the Investing in Canadian Infrastructure Program and has tax funding from Queen’s Park and Ottawa.
Krcel said the cost of the renovations is in part due to the amount of work needed in a commercial building, as well as generally inflated construction costs.
“We’ve noticed price increases on everything we do,” he said.
WORK TO BEGIN THIS WINTER
The work is expected to begin over the winter, with no impact to transit service.
Office staff to be moved into a temporary facility until it’s complete.The interior of Timmins Transit’s Spruce Street South terminal is overdue for an upgrade, according to city officials.
First built more than a century ago as an Ontario National Railway station, public works manager Ken Krcel said the city hadn’t done any major renovations since purchasing the building in 2010.
He said several areas need improving and that it will be a more than $1.4 million project.
“It includes reclining the walls, new plumbing, new heating and any asbestos remediation that (workers) may come across,” Krcel said.
The terminal’s office space is limited, which the city feels can be fixed by adjusting the building’s layout and converting some storage rooms into offices.
Krcel also noted a safety issue with the terminal’s public washrooms. Their antiquated doors lock from the inside, which he said has lent itself to vandalism and mischief.
BATHROOMS VANDALIZED
“People have gone in, locked themselves in there and basically vandalized the washrooms, wrecked them and left them in a state that the next person from the public going in, it’s unusable and they’re unsafe,” Krcel said.
“They’ll be designed without physical doors, just the bathroom stall doors. A series of corridors that would prevent us from losing access to the washrooms at any time.”
He said the renovations won’t affect the exterior of the building, which has largely remained in its original condition, with signs of expansions before the city took it over.
The chair of the municipal heritage committee, Nicola Alexander, said the terminal stands out as a reminder of the city’s past, when rail was the only way in and out of the area.
“Some of the heritage features of this building are the original face brick, these beautiful brackets that are holding up the eaves,” Alexander said.
“You can still see the original foundation stone, with the carving commemorating the opening of this building in 1916.”
The interior renovations will be paid for with funding from the Investing in Canadian Infrastructure Program and has tax funding from Queen’s Park and Ottawa.
Krcel said the cost of the renovations is in part due to the amount of work needed in a commercial building, as well as generally inflated construction costs.
“We’ve noticed price increases on everything we do,” he said.
The work is expected to begin over the winter, with no impact to transit service.
Office staff to be moved into a temporary facility until it’s complete.
CTVNews.ca Top Stories
More than 115 cases of eye damage reported in Ontario after solar eclipse
More than 115 people who viewed the solar eclipse in Ontario earlier this month experienced eye damage after the event, according to eye doctors in the province.
Toxic testing standoff: Family leaves house over air quality
A Sherwood Park family says their new house is uninhabitable. The McNaughton's say they were forced to leave the house after living there for only a week because contaminants inside made it difficult to breathe.
Decoy bear used to catch man who illegally killed a grizzly, B.C. conservation officers say
A man has been handed a lengthy hunting ban and fined thousands of dollars for illegally killing a grizzly bear, B.C. conservation officers say.
B.C. seeks ban on public drug use, dialing back decriminalization
The B.C. NDP has asked the federal government to recriminalize public drug use, marking a major shift in the province's approach to addressing the deadly overdose crisis.
OPP responds to apparent video of officer supporting anti-Trudeau government protestors
The Ontario Provincial Police (OPP) says it's investigating an interaction between a uniformed officer and anti-Trudeau government protestors after a video circulated on social media.
An emergency slide falls off a Delta Air Lines plane, forcing pilots to return to JFK in New York
An emergency slide fell off a Delta Air Lines jetliner shortly after takeoff Friday from New York, and pilots who felt a vibration in the plane circled back to land safely at JFK Airport.
Sophie Gregoire Trudeau on navigating post-political life, co-parenting and freedom
Sophie Gregoire Trudeau says there is 'still so much love' between her and Prime Minister Justin Trudeau, as they navigate their post-separation relationship co-parenting their three children.
Last letters of pioneering climber who died on Everest reveal dark side of mountaineering
George Mallory is renowned for being one of the first British mountaineers to attempt to scale the dizzying heights of Mount Everest during the 1920s. Nearly a century later, newly digitized letters shed light on Mallory’s hopes and fears about ascending Everest.
Loud boom in Hamilton caused by propane tank, police say
A loud explosion was heard across Hamilton on Friday after a propane tank was accidentally destroyed and detonated at a local scrap metal yard, police say.