Supply chain pressures, startup delays hike budget for Sault Downtown Plaza to $11.6M
Meeting on Monday, city councillors in Sault Ste. Marie will be asked to approve another budget increase for the Downtown Plaza project.
Originally pegged at $6.6 million in 2019, councillors approved a revised estimate of more than $8.4 million in May 2021. That increased to $10.19 million in May 2022 after bids on the project came in higher than expected.
A staff report at the time cited soaring inflation in the construction industry, with residential construction costs up an estimated 21.7 per cent and non-residential up by 11.2 per cent.
The city was also unsuccessful in its bid to get $2 million in funding from the Northern Ontario Heritage Fund Corp. (NOHFC) for the project.
However, fundraising reached a total of $1.1 million and the project received $500,000 from FedNor and $250,000 from a provincial rural economic development program.
A staff report for Monday’s meeting said global supply pressures are causing delays and driving up costs.
“The most significant delay was the availability of equipment and materials for the outdoor rink feature,” the report said.
“These supply chain issues have delayed the ability to pour the rink until the spring timeframe when the frost is out of the ground. Other delays impacted the project schedule and necessitated pouring of some concrete elements into the winter months which requires additional heating and hoarding costs to be incurred.”
To partially offset the latest cost increase, the report suggests using $660,000 previously earmarked for the Mill Market project. That money is no longer needed because the project successfully applied for funding from upper levels of government.
The remainder of the cost increase would be funded by delaying plans to replace the ‘A’ dock at the Bellevue Marina.
“Staff have reviewed and believe that the ‘A’ dock can be maintained and operated safely for another season,” the report said.
By using these funding sources, the report said no increase to property taxes would be required to move forward with the plaza.
“The request for additional funding for the plaza project at this time is required to continue with project construction and accommodate current change orders and fees,” the report said.
“Should the Mill Market be successful in their other applications, this will further reduce the city share in the project.”
Read the full report here.
CTVNews.ca Top Stories
'We will exercise fiscal restraint': Freeland outlines priorities ahead of 2023 federal budget
The coming 2023 federal budget will 'exercise fiscal restraint' while also making 'significant' investments in health and building Canada's clean economy, Deputy Prime Minister and Finance Minister Chrystia Freeland said Monday.

3 people stabbed at Halifax-area high school; 1 person in custody
Police in Halifax say three people have been stabbed and a student is in custody following a weapons complaint at a high school in Bedford, N.S.
W5 Investigates | How did a healthy teen die at a minor hockey camp?
The parents of young Ontario hockey player Ben Teague have been searching for answers since he died while at a team retreat in 2019. The mystery about what happened and the code of silence in hockey culture is explored in CTV W5's 'What Happened to Ben,' on CTVNews.ca and W5's official YouTube channel.
Conservatives forcing MPs to vote on striking new foreign interference study
In an effort to keep the foreign interference story at the forefront, and to do an apparent end run around the Liberal filibuster blocking one study from going ahead, Conservative Leader Pierre Poilievre has forced the House to spend the day debating a motion instructing an opposition-dominated House committee to strike its own review.
Spring backwards? Why next spring will come earlier than it has in nearly 130 years
In the previous century, the spring equinox typically fell on March 21, but the first day of spring has slowly been moving. Here's why next year it will fall on March 19, for the first time since the 1800s.
Nexus program to resume by April 24 after yearlong standoff
The federal government says the Nexus trusted-traveller program will fully ramp back up within five weeks, allowing frequent border crossers to complete their applications and speed up their trips.
Amazon cuts 9,000 more jobs, bringing 2023 total to 27,000
Amazon plans to eliminate 9,000 more jobs in the next few weeks, CEO Andy Jassy said in a memo to staff on Monday.
Parliamentary committee summons Mark Zuckerberg over Meta's threat to block news
A parliamentary committee has decided to invite the testimony of Meta CEO Mark Zuckerberg, whose company operates Facebook and Instagram.
Donald Trump's call for protests gets muted reaction by supporters
Former U.S. President Donald Trump's calls for protests ahead of his anticipated indictment in New York have generated mostly muted reactions from supporters, with even some of his most ardent loyalists dismissing the idea as a waste of time or a law enforcement trap.