A Sudbury construction company is suing the Ontario government, arguing the contract it signed to expand part of Highway 69 incorrectly estimated the amount of rock that would be leftover at the end of the project.
The $20 million suit centres on whether the province incorrectly estimated the amount of rock, as Bot Construction claims, or whether the excess rock is a result of the way it was blasted, as the Ontario government claims.
Lawyers for the company argue the excess rock is a result of a design error, as well as errors estimating the extent to which crushed and broken rock takes up more volume than rock sitting in the bank.
Bot argues that its bid for the work was much lower than it should have been because of the errors. It said the amount of rock it had to deal with was "approximately 26 times more than was estimated."
"The plaintiffs’ position is that this case is fundamentally about whether two pieces of information provided by the defendant to bidders on the contract were incorrect and if so, was the price the plaintiffs’ bid for the contract artificially deflated by its reliance on that incorrect information," said a court transcript of the latest hearing on the case, released May 31.
In response, lawyers from the province said Bot is responsible for the excess rock because "of the way it conducted the work on the project."
"The defendant asserts that the source of the additional rock is the drilling and blasting techniques employed by the plaintiffs and its subcontractors," the transcript said.
"Specifically, one source of additional rock would be over-blasting by the plaintiffs: blasting beyond the design lines of the contract, also referred to as 'overbreak.' While over-blasting is permitted, disposal of any additional rock generated by over-blasting would be the responsibility of the plaintiffs."
The province argued that Bot should have to provide extensive documentation on their blasting techniques to determine whether that was the cause of the excess rock.
But Bot argued their case is based on arguments the information provided the province in the contract was incorrect, leading the company to bid too low. Specific blasting techniques, they argue, aren't relevant.
While largely finding for Bot, the judge in the case said the company had to say whether an expert report they had prepared would allow them to answer how much they would have bid on the contract at the time, if the alleged design errors had not been made.
"If the report did provide them with sufficient information/data to answer how they would have bid but for the design error, they must also answer that question," the judge ruled.
"If they do not have the data/ information to respond, they are not required to do so, because that would impose an undue burden of work."
Read the full transcript here.
CTVNews.ca Top Stories
'A step forward': New screening criteria for sperm donors takes effect
Canadians looking to grow their families with the assistance of sperm or egg donations should soon have more options for donors as the federal health agency does away with longstanding restrictions criticized as discriminatory.
What is whooping cough and should Canadians be concerned as Europe declares outbreak?
There is currently a whooping cough epidemic in Europe, with 10 times as many cases compared to the previous two years. While an outbreak has not been declared nationwide in Canada, whooping cough is regularly detected in the country.
Ontario Provincial Police arrest 64 suspects in child sexual exploitation investigation
Ontario Provincial Police say 64 suspects are facing a combined 348 charges in connection with a series of child sexual exploitation investigations that spanned the province.
'Summer of discontent': Federal unions vow to fight new 3-day a week office mandate
Federal unions are launching legal challenges and encouraging public sector workers to file "tens of thousands" of grievances over the new mandate requiring federal workers to return to the office at least three days a week in the fall.
Pfizer agrees to settle more than 10,000 Zantac lawsuits in U.S.: Bloomberg News
Pfizer has agreed to settle more than 10,000 lawsuits about cancer risks related to the now discontinued heartburn drug Zantac, Bloomberg News reported on Wednesday, citing people familiar with the deal.
Watch fighter jet pilots pummel fake enemy ship off coast of Philippines
The United States and Philippines held annual joint-training drills just off the Southeast Asian nation’s western coast on Wednesday. Military forces sunk a 'mock' enemy warship – the BRP Lake Caliraya, which was a decommissioned tanker made in China.
U.S. presidential candidate RFK Jr. had a brain worm, has recovered, campaign says
Independent U.S. presidential candidate Robert F. Kennedy Jr. had a parasite in his head more than a decade ago, but has fully recovered, his campaign said, after the New York Times reported about the ailment.
'Ozempic babies': Reports of surprise pregnancies raise new questions about weight loss drugs
Numerous women have shared stories of 'Ozempic babies' on social media. But the joy some experience in discovering pregnancies may come with anxiety about the unknowns.
Rookie goalie Arturs Silovs to start for Canucks in Game 1 vs. Oilers
Rookie goalie Arturs Silovs will start in net for the Canucks as Vancouver kicks off a second-round series against the Edmonton Oilers Wednesday night.