'Dial before you dig' backlog causing major construction delays in Timmins
The Timmins Construction Association is alerting the Ontario government about a chronic problem that is causing major construction delays.
Under Ontario law, individuals and construction companies must take steps to ensure no underground infrastructure will be affected by their construction project.
Better known as 'dial before you dig,' it's illegal to begin digging for most construction projects until it has been determined there are no electrical, telephone, water or other underground infrastructure that could be damaged.
A request is made to Ontario One Call, which informs the utility or company. In turn, the utility sends out a locater who paints or puts flags on the areas where the infrastructure is situated.
The process is supposed to take a few days, but Jamie Clarke, president of the 100-member Timmins Construction Association, said the process can now take months.
"We are writing to inform you of one of the largest barriers to new and existing infrastructure expansions and builds in northern Ontario," Clarke said in an open letter to Kaleed Rasheed, Ontario's Minister for Public and Business Service Delivery.
"Any and all excavating of a new building, repairing buried infrastructure, landscaping, residential paving, building concrete slabs, or anything else that requires you to break ground, you must contact Ontario One Call at a minimum of five days prior to your excavation."
However, builders who submit a request in Timmins are waiting as long as three months, Clarke said.
It's an added delay – and cost – to builders at a time when supply chain problems generally are pushing up costs, he said.
"Minister, northern Ontario has a very narrow window of opportunity to complete critical infrastructure projects," Clarke said in his letter.
"The massive financial burden these delays bring to our firms can heavily impact the outcome of the project and our community's ability to encourage new investment in the future."
Ian Simpson, spokesperson for Ontario One Call, told CTV News that above all, it is key for everyone to dial before they dig for a number of safety reasons.
"Whether it's planting a tree, putting in a pool or a major construction … they have to request a 'locate' by law," Simpson said.
"The only way to do that is to go through Ontario One Call."
One Call is the 'middle man' in the process, Simpson said. Their job is to inform the utility that they have received a request. The utility then sends someone out to clear the area, or mark the areas where there is infrastructure.
"Legally, they have to respond with a locate," Simpson said.
"It is them that comes out to someone's property or if it's a major project in order to put the locate markings on the ground."
While made worse by the COVID-19 pandemic, he said delays in fulfilling locate requests are nothing new. One of the challenges is the fact multiple utilities may have to do locates for the same project.
BIGGEST CHALLENGE
"If you have three utilities involved, you legally can't dig until all three of them respond with the locate," Simpson said.
"So even if two of your local utility companies get out there and do it within the legal time frame -- which is five business days to be complying with the law – you still can't legally dig."
The biggest challenge is usually staffing, he said, with utilities not having enough qualified people available to keep up with requests.
"Primarily, it would be a resource issue," Simpson said.
"If they don't have enough staff to go out with the demand of locate requests coming in, then they may fall behind and that's what could be creating these delays now."
In April, the province passed changes to the law aimed at streamlining the process and clearing some of the backlog. For example, Simpson said in the past, companies building in the same area couldn't share a locate request and had to issue them separately.
"So the utilities (had to) send two different groups at two different times for the exact same area," he said.
"Now they can share those locates."
There are also plans to hire a lot more people to do the locates, but Simpson said there is significant training involved and it could take some time.
"We need really well-trained utility locators because … what they do really impacts the safety of Ontarians," he said.
"If they don't get it right, there's a risk that someone could get severely hurt -- and no one wants anyone to get hurt. And no one wants a gas pipe to get hit, no one wants electricity to get hit, no one wants water to get hit."
CTVNews.ca Top Stories
'Still so much love between us,' Sophie Gregoire Trudeau says of Prime Minister Justin Trudeau
Sophie Gregoire Trudeau says there is 'still so much love' between her and Prime Minister Justin Trudeau, as they navigate their post-separation relationship co-parenting their three children.
What to know about avian influenza in dairy cows and the risk to humans
Why is H5N1, or bird flu, a concern, how does it spread, and is there a vaccine? Here are the answers to some frequently asked questions about avian influenza.
'I was scared': Ontario man's car repossessed after missing two repair loan payments
An Ontario man who took out a loan to pay for auto repairs said his car was repossessed after he missed two payments.
opinion The special relationship between King Charles and the Princess of Wales
Royal commentator Afua Hagan writes that when King Charles recently admitted Catherine to the Order of the Companions of Honour, it not only made history, but it reinforced the strong bond between the King and his beloved daughter-in-law.
Pro-plastic lobbyist presence at UN talks is 'troubling,' say advocates
Environmentalist groups are sounding the alarm about a steep increase in the number of pro-plastic lobbyists at the UN pollution talks taking place this week.
'Too young to have breast cancer': Rates among young Canadian women rising
Breast cancer rates are rising in Canada among women in their 20s, 30s and 40s, according to research by the University of Ottawa (uOttawa).
Charlie Woods, son of Tiger, shoots 81 in U.S. Open qualifier
Charlie Woods failed to advance in a U.S. Open local qualifying event Thursday, shooting a 9-over 81 at Legacy Golf & Tennis Club.
$70M Lotto Max winners kept prize a secret from family for 2 months
During a special winner celebration near their hometown, Doug and Enid shared the story of how they discovered they were holding a Lotto Max ticket worth $70 million and how they kept this huge secret for so long.
Trump's lawyers grill ex-tabloid publisher as 1st week of hush money trial testimony nears a close
After prosecutors' lead witness painted a tawdry portrait of “catch-and-kill” tabloid schemes, defence lawyers in Donald Trump's criminal trial on Friday sought to dig into an account of the former publisher of the National Enquirer and his efforts to protect Trump from negative stories during the 2016 election.