'Dial before you dig' backlog causing major construction delays in Timmins
The Timmins Construction Association is alerting the Ontario government about a chronic problem that is causing major construction delays.
Under Ontario law, individuals and construction companies must take steps to ensure no underground infrastructure will be affected by their construction project.
Better known as 'dial before you dig,' it's illegal to begin digging for most construction projects until it has been determined there are no electrical, telephone, water or other underground infrastructure that could be damaged.
A request is made to Ontario One Call, which informs the utility or company. In turn, the utility sends out a locater who paints or puts flags on the areas where the infrastructure is situated.
The process is supposed to take a few days, but Jamie Clarke, president of the 100-member Timmins Construction Association, said the process can now take months.
"We are writing to inform you of one of the largest barriers to new and existing infrastructure expansions and builds in northern Ontario," Clarke said in an open letter to Kaleed Rasheed, Ontario's Minister for Public and Business Service Delivery.
"Any and all excavating of a new building, repairing buried infrastructure, landscaping, residential paving, building concrete slabs, or anything else that requires you to break ground, you must contact Ontario One Call at a minimum of five days prior to your excavation."
However, builders who submit a request in Timmins are waiting as long as three months, Clarke said.
It's an added delay – and cost – to builders at a time when supply chain problems generally are pushing up costs, he said.
"Minister, northern Ontario has a very narrow window of opportunity to complete critical infrastructure projects," Clarke said in his letter.
"The massive financial burden these delays bring to our firms can heavily impact the outcome of the project and our community's ability to encourage new investment in the future."
Ian Simpson, spokesperson for Ontario One Call, told CTV News that above all, it is key for everyone to dial before they dig for a number of safety reasons.
"Whether it's planting a tree, putting in a pool or a major construction … they have to request a 'locate' by law," Simpson said.
"The only way to do that is to go through Ontario One Call."
One Call is the 'middle man' in the process, Simpson said. Their job is to inform the utility that they have received a request. The utility then sends someone out to clear the area, or mark the areas where there is infrastructure.
"Legally, they have to respond with a locate," Simpson said.
"It is them that comes out to someone's property or if it's a major project in order to put the locate markings on the ground."
While made worse by the COVID-19 pandemic, he said delays in fulfilling locate requests are nothing new. One of the challenges is the fact multiple utilities may have to do locates for the same project.
BIGGEST CHALLENGE
"If you have three utilities involved, you legally can't dig until all three of them respond with the locate," Simpson said.
"So even if two of your local utility companies get out there and do it within the legal time frame -- which is five business days to be complying with the law – you still can't legally dig."
The biggest challenge is usually staffing, he said, with utilities not having enough qualified people available to keep up with requests.
"Primarily, it would be a resource issue," Simpson said.
"If they don't have enough staff to go out with the demand of locate requests coming in, then they may fall behind and that's what could be creating these delays now."
In April, the province passed changes to the law aimed at streamlining the process and clearing some of the backlog. For example, Simpson said in the past, companies building in the same area couldn't share a locate request and had to issue them separately.
"So the utilities (had to) send two different groups at two different times for the exact same area," he said.
"Now they can share those locates."
There are also plans to hire a lot more people to do the locates, but Simpson said there is significant training involved and it could take some time.
"We need really well-trained utility locators because … what they do really impacts the safety of Ontarians," he said.
"If they don't get it right, there's a risk that someone could get severely hurt -- and no one wants anyone to get hurt. And no one wants a gas pipe to get hit, no one wants electricity to get hit, no one wants water to get hit."
CTVNews.ca Top Stories
Breast cancer screening should start at age 40, Canadian Cancer Society says
The Canadian Cancer Society says all provinces and territories should lower the starting age for breast cancer screening to 40.
DEVELOPING Live updates as Stormy Daniels testifies at Trump hush money trial
Adult film star Stormy Daniels is on the stand a second time Thursday as former U.S. president Donald Trump’s hush money case continues in Manhattan. Follow live updates here.
Ontario family receives massive hospital bill as part of LTC law, refuses to pay
A southwestern Ontario woman has received an $8,400 bill from a hospital in Windsor, Ont., after she refused to put her mother in a nursing home she hated -- and she says she has no intention of paying it.
Canadian-Israeli man shot dead in Egypt; claim links killing to Gaza
A Canadian man 'of Jewish Israeli descent' has been shot dead in the Egyptian city of Alexandria in a suspected criminal case, a security source said, while a previously unknown militant group said it carried out the attack in reaction to the war in Gaza.
Here are the ultraprocessed foods you most need to avoid, according to a 30-year study
Studies have shown that ultraprocessed foods can have a detrimental impact on health. But 30 years of research show they don’t all have the same impact.
Ontario man frustrated after $3,500 paving job leaves driveway in shambles
An Ontario man considering having his driveway paved received a quote from a company for $7,000, but then, another paver in the neighbourhood knocked on his door and offered half that rate.
Why these immigrants to Canada say they're thinking about leaving, or have already moved on
For some immigrants, their dreams of permanently settling in Canada have taken an unexpected twist.
BREAKING Sheldon Keefe out as head coach of Toronto Maple Leafs
The Toronto Maple Leafs have fired head coach Sheldon Keefe. The team made the announcement Thursday after the Original Six franchise lost to the Boston Bruins in seven games in the first round of the Stanley Cup playoffs.
Boeing 737 catches fire and skids off the runway at a Senegal airport, injuring 10 people
A Boeing 737-300 plane carrying 85 people skidded off a runway at the airport in Dakar, Senegal's capital, injuring 10 people, according to the transport minister, an airline safety group and footage from a passenger that showed the aircraft on fire.