Elliot Lake city councillors frustrated after latest arena update
Elliot Lake city councillors appeared to be visibly frustrated on Monday night during a progress update on the Centennial Arena, which has been shuttered since the fall.
Staff was giving council the latest on the situation involving the beleaguered facility after engineers deemed the arena structurally unsafe last September.
The recommendation facing council was to approve the use of the negotiation method to sole source the design of structural repairs through Wood Research and Development Canada with a limit of $186,900.
What they got, however, was a report that outlined some of the delays and challenges staff has been facing.
One of the contractors informed staff in March they would be unable to proceed under the current agreement.
Council questioned staff about the timeline or lack thereof, and when they might see some costs associated with the project.
"I share your disappointment and frustration. The dude sat right in that TV screen and I asked him outright, 'Do you do this often? Do you share responsibilities with other companies,'" Mayor Andrew Wannan said to the city manager.
"And he assured us they do it all the time. To have this come back because of legal is a bit of a slap in the face."
Wannan also questioned staff about why council was just hearing about the delays involving the contractor now.
He was told by the manager involved, staff was in the process of bringing something concrete back to council so they could get further direction.
"It’s such an important part of Elliot Lake, as we saw with 'Kraft Hockeyville'. I mean not everybody cared, but I’d say 97 per cent at least did and we just, we just have to," acting manager of public works Bill Golding said.
"I’m just really reiterating what Mayor Wannan said. We just, whatever it takes, we have to get some construction going on there, not the shoring part, we need to say 'Oh they’re changing the beams.' We just gotta get this thing going."
Despite the delays, Golding told councillors he’s still hopeful they can make the deadline of having the arena ready by the 4th quarter of 2024.
New councillor Helen Lefebvre suggested Golding go back to the contractors involved and try to confirm or push them towards some hard targets to achieve.
"We got a lot of stuff we have to figure out. I’m trying to pull every trick I can to get things moving as fast as I can," Golding told the councillors.
Since installing the sensors in the building, he added, staff has been recording a fair bit of movement over the past month on the site.
"On March 8, they got no less than eight alarms that day," said Golding, who told councillors he would be very surprised if the footings to the arena had been checked five years ago.
He said he stands by his initial decision to have both contractors involved, he’s hoping a new project design agreement, which is expected in the coming weeks, will get things moving.
In his report, Golding writes repairing the facility is still the most prudent way to address the situation.
CTVNews.ca Top Stories
Tanks reach Rafah's centre as Israel presses assault despite global scrutiny
Israeli tanks reached the centre of Rafah for the first time on Tuesday, witnesses said, three weeks into a ground operation in the southern Gaza city that has sparked global condemnation.
More Canadians only making minimum payment on credit cards: TransUnion
Some Canadians are seeing their credit card balances grow as the cost-of-living crisis and higher interest rates eat into household budgets, a new report shows.
Tornado touches down west of the Island of Montreal
Emergency services in the town of Rigaud, Que. are investigating after a tornado touched down shortly after 5:30 p.m. on Friday.
What a CBSA strike could look like, according to an expert
Slowed or interrupted travel, the passing of goods and significantly restricted borders should be expected if Canadian border workers take upcoming strike action.
Arm of mummy came off after mishandling by museum staff: Mexican government
Mexico's federal archaeology agency on Monday accused the conservative-governed city of Guanajuato of mistreating one of the country’s famous mummified 19th century bodies.
DEVELOPING In Trump's hush money trial, prosecutors and defence lawyers are poised to make final pitch to jury
Prosecutors and defence lawyers in Donald Trump's hush money trial are set to deliver closing arguments to the jury Tuesday, each side looking to score final points with the panel before it starts deliberating the fate of the first former American president to be charged with felony crimes.
Five of Ontario's top 10 worst roads are located in the Toronto area
A new pothole-riddled street in Hamilton has taken the top spot for the worst road in Ontario, according to a new list released by the Canadian Automotive Association (CAA) on Tuesday.
Teen was doing homework at family's Mississauga, Ont. restaurant when gunman opened fire: testimony
The 13-year-old sister of a young man killed in the attack on her family’s Mississauga restaurant in 2021 took the stand in a Brampton courthouse on Monday to describe the terrifying moments of coming under fire.
B.C. senior prepares to move due to devastating effects of fraud
A Courtenay, B.C., senior is downsizing and packing to move as she comes to accept she can no longer afford to stay in her home, after falling victim to a scam that robbed her of her life savings worth more than $100,000.