Elliot Lake city councillors frustrated after latest arena update
Elliot Lake city councillors appeared to be visibly frustrated on Monday night during a progress update on the Centennial Arena, which has been shuttered since the fall.
Staff was giving council the latest on the situation involving the beleaguered facility after engineers deemed the arena structurally unsafe last September.
The recommendation facing council was to approve the use of the negotiation method to sole source the design of structural repairs through Wood Research and Development Canada with a limit of $186,900.
What they got, however, was a report that outlined some of the delays and challenges staff has been facing.
One of the contractors informed staff in March they would be unable to proceed under the current agreement.
Council questioned staff about the timeline or lack thereof, and when they might see some costs associated with the project.
"I share your disappointment and frustration. The dude sat right in that TV screen and I asked him outright, 'Do you do this often? Do you share responsibilities with other companies,'" Mayor Andrew Wannan said to the city manager.
"And he assured us they do it all the time. To have this come back because of legal is a bit of a slap in the face."
Wannan also questioned staff about why council was just hearing about the delays involving the contractor now.
He was told by the manager involved, staff was in the process of bringing something concrete back to council so they could get further direction.
"It’s such an important part of Elliot Lake, as we saw with 'Kraft Hockeyville'. I mean not everybody cared, but I’d say 97 per cent at least did and we just, we just have to," acting manager of public works Bill Golding said.
"I’m just really reiterating what Mayor Wannan said. We just, whatever it takes, we have to get some construction going on there, not the shoring part, we need to say 'Oh they’re changing the beams.' We just gotta get this thing going."
Despite the delays, Golding told councillors he’s still hopeful they can make the deadline of having the arena ready by the 4th quarter of 2024.
New councillor Helen Lefebvre suggested Golding go back to the contractors involved and try to confirm or push them towards some hard targets to achieve.
"We got a lot of stuff we have to figure out. I’m trying to pull every trick I can to get things moving as fast as I can," Golding told the councillors.
Since installing the sensors in the building, he added, staff has been recording a fair bit of movement over the past month on the site.
"On March 8, they got no less than eight alarms that day," said Golding, who told councillors he would be very surprised if the footings to the arena had been checked five years ago.
He said he stands by his initial decision to have both contractors involved, he’s hoping a new project design agreement, which is expected in the coming weeks, will get things moving.
In his report, Golding writes repairing the facility is still the most prudent way to address the situation.
CTVNews.ca Top Stories
Montreal man on the hook for thousands of dollars after a feature on his Tesla caused an accident
A Montreal man is warning Tesla drivers about using the Smart Summon feature after his vehicle hit another in a parking lot.
Denial and uncertainty are looming over a Biden-Trump rematch 6 months out from U.S. Election Day
Exactly six months before Election Day, Biden and Trump are locked in the first contest in 112 years with a current and former president competing for the White House. It's a race that is at once deeply entrenched and highly in flux as many voters are only just beginning to embrace the reality of the 2024 campaign.
Israel closes Gaza crossing after Hamas attack and vows military operation 'in the very near future'
Israel closed its main crossing point for delivering badly needed humanitarian aid for Gaza on Sunday after Hamas militants attacked it, reportedly wounding several Israelis, while the defense minister warned of "a powerful operation in the very near future in Rafah and other places across all of Gaza."
‘Love has no boundaries’: Sask. couple in their 90s and 80s get married
Eighty-two-year-old Susan Neufeldt and 90-year-old Ulrich Richter are no spring chickens, but their love blossomed over the weekend with their wedding at Pine View Manor just outside of Rosthern.
opinion You don't need to be an influencer to earn income from social media
How legitimate are claims by some content creators that the average person can earn passive income from social media platforms like TikTok and Instagram? Personal finance columnist Christopher Liew says it's quite possible, if you're willing to put in the initial time and effort.
Madonna's biggest-ever concert transforms Rio's Copacabana beach into a massive dance floor
Madonna put on a free concert on Copacabana beach Saturday night, turning Rio de Janeiro's vast stretch of sand into an enormous dance floor teeming with a multitude of her fans.
No proof man lied to brother about number of kittens born in litter, B.C. tribunal rules
A man was denied a $5,000 payout from his brother after a B.C. tribunal dismissed his claim disputing how many kittens were born in a litter.
Should you save or splurge on makeup this summer?
If you're wondering whether you should splurge or save when it comes to buying skincare products and makeup this summer, we got some answers for you.
Chemical spill could be cause of stinky water in Puslinch, Ont., new report says
People living in Puslinch, Ont. may have the answer to why their water smelled so bad last year.