'Dial before you dig' backlog causing major construction delays in Timmins
The Timmins Construction Association is alerting the Ontario government about a chronic problem that is causing major construction delays.
Under Ontario law, individuals and construction companies must take steps to ensure no underground infrastructure will be affected by their construction project.
Better known as 'dial before you dig,' it's illegal to begin digging for most construction projects until it has been determined there are no electrical, telephone, water or other underground infrastructure that could be damaged.
A request is made to Ontario One Call, which informs the utility or company. In turn, the utility sends out a locater who paints or puts flags on the areas where the infrastructure is situated.
The process is supposed to take a few days, but Jamie Clarke, president of the 100-member Timmins Construction Association, said the process can now take months.
"We are writing to inform you of one of the largest barriers to new and existing infrastructure expansions and builds in northern Ontario," Clarke said in an open letter to Kaleed Rasheed, Ontario's Minister for Public and Business Service Delivery.
"Any and all excavating of a new building, repairing buried infrastructure, landscaping, residential paving, building concrete slabs, or anything else that requires you to break ground, you must contact Ontario One Call at a minimum of five days prior to your excavation."
However, builders who submit a request in Timmins are waiting as long as three months, Clarke said.
It's an added delay – and cost – to builders at a time when supply chain problems generally are pushing up costs, he said.
"Minister, northern Ontario has a very narrow window of opportunity to complete critical infrastructure projects," Clarke said in his letter.
"The massive financial burden these delays bring to our firms can heavily impact the outcome of the project and our community's ability to encourage new investment in the future."
Ian Simpson, spokesperson for Ontario One Call, told CTV News that above all, it is key for everyone to dial before they dig for a number of safety reasons.
"Whether it's planting a tree, putting in a pool or a major construction … they have to request a 'locate' by law," Simpson said.
"The only way to do that is to go through Ontario One Call."
One Call is the 'middle man' in the process, Simpson said. Their job is to inform the utility that they have received a request. The utility then sends someone out to clear the area, or mark the areas where there is infrastructure.
"Legally, they have to respond with a locate," Simpson said.
"It is them that comes out to someone's property or if it's a major project in order to put the locate markings on the ground."
While made worse by the COVID-19 pandemic, he said delays in fulfilling locate requests are nothing new. One of the challenges is the fact multiple utilities may have to do locates for the same project.
BIGGEST CHALLENGE
"If you have three utilities involved, you legally can't dig until all three of them respond with the locate," Simpson said.
"So even if two of your local utility companies get out there and do it within the legal time frame -- which is five business days to be complying with the law – you still can't legally dig."
The biggest challenge is usually staffing, he said, with utilities not having enough qualified people available to keep up with requests.
"Primarily, it would be a resource issue," Simpson said.
"If they don't have enough staff to go out with the demand of locate requests coming in, then they may fall behind and that's what could be creating these delays now."
In April, the province passed changes to the law aimed at streamlining the process and clearing some of the backlog. For example, Simpson said in the past, companies building in the same area couldn't share a locate request and had to issue them separately.
"So the utilities (had to) send two different groups at two different times for the exact same area," he said.
"Now they can share those locates."
There are also plans to hire a lot more people to do the locates, but Simpson said there is significant training involved and it could take some time.
"We need really well-trained utility locators because … what they do really impacts the safety of Ontarians," he said.
"If they don't get it right, there's a risk that someone could get severely hurt -- and no one wants anyone to get hurt. And no one wants a gas pipe to get hit, no one wants electricity to get hit, no one wants water to get hit."
CTVNews.ca Top Stories
Weather alerts issued for 7 provinces, 1 territory
Warnings of up to 60 millimetres of rain and other alerts have been issued for seven Canadian provinces and one territory ahead of the Easter weekend.
He didn't trust police but sought their help anyway. Two days later, he was dead
Jameek Lowery was among more than 330 Black people who died after police stopped them with tactics that aren’t supposed to be deadly, like physical restraint and use of stun guns, The Associated Press found.
Luxury cruise line selling world cruise suite for US$1.7 million
Luxury operator Regent Seven Seas Cruises is raising their price tag to eye-watering levels, with a suite on an upcoming 140-day world voyage costing US$1.7 million.
CRA no longer requiring 'bare trust' reporting in 2023 tax return
The Canada Revenue Agency announced Thursday it will not require 'bare trust' reporting from Canadians that it introduced for the 2024 tax season, just four days before the April 2 deadline.
A Filipino villager is nailed to a cross for the 35th time on Good Friday to pray for world peace
A Filipino villager has been nailed to a wooden cross for the 35th time to reenact Jesus Christ’s suffering in a brutal Good Friday tradition he said he would devote to pray for peace in Ukraine, Gaza and the disputed South China Sea.
Fluid in eye cells can 'boil' if you watch the eclipse without protection: expert
Millions of people in parts of Eastern and Atlantic Canada will be able to see the rare solar eclipse happening on April 8. But they should only look up if they have proper eye protection, experts say.
'Oppenheimer' finally premieres in Japan to mixed reactions and high emotions
'Oppenheimer' finally premiered Friday in the nation where two cities were obliterated 79 years ago by the nuclear weapons invented by the American scientist who was the subject of the Oscar-winning film. Japanese filmgoers' reactions understandably were mixed and highly emotional.
Do these exercises for core strength if you can't stomach doing planks
Planks are one of the most effective exercises for strengthening your midsection, as they target all of your major core muscles: the transverse abdominis, rectus abdominis, external obliques and internal obliques. Yet despite the popularity of various 10-minute plank challenges, planking is actually one of the most dreaded core exercises, according to many fitness experts.
Sunshine list: These were the Ontario public sector's highest earners in 2023
Ontario released its annual sunshine list Thursday afternoon, noting that the largest year-over-year increases were in hospitals, municipalities, and post-secondary sectors.