Cost of Sudbury’s Junction East project jumps to over $93M
No plans have been confirmed, but following a special council meeting Tuesday night, Sudbury’s proposed Junction East project could come with a new total price tag of $93.2 million.
The community hub, expected to be built downtown on Shaughnessy Street beside Sudbury’s Theatre Centre, was first put forward in 2016 and it has only grown since.
Initial estimates for the project, which is expected to be completed in 2024, were about $46 million for a 62,000 square-foot building according to the city website. However, Tuesday’s update saw the size increase to a 104,000 square-foot space along with a price tag that has more than doubled in cost.
"There are a number of reasons for the increased costs from the original estimate," said Ian Wood, the executive director of the City of Greater Sudbury.
"First of all, it was just an estimate that was not based on a real building, but just based on an approximation value. It was also five years ago, so there has been significant construction cost increases over the past five years and the numbers that we presented to council also include a contingency against cost increases even in the future."
In an email to CTV News Thursday morning, city spokesperson Sacha Novack said the 62,000 square footage previously listed on the project's website "refers to the net square footage identified in the original 2017 project estimation completed by Lord Cultural Resources."
Screenshot of Google search result of Sudbury's Junction East project. May 4/22 (Alana Pickrell/CTV Northern Ontario)
"It does not include items such as common areas, corridors, washrooms, stairwells, mechanical rooms, elevators or even the thickness of interior and exterior walls. It is related to what is called the functional program or detailed space requirements. When these items are accounted for, the Lord Report provides an estimated building size, or gross square footage, of 92,700 square feet," Novack said.
"The functional program space for the Art Gallery and Library have remained constant since 2017. The 11,000 square foot increase is related to the inclusion of the Sudbury Multicultural Folk Arts Association into the building, the space required for the inclined walkway recommendation and some additional common space in the lobby area which is best practice for this type of large and ionic facility."
When completed, Junction East will be home to the main library, the Multicultural and Folk Arts Association and the Art Gallery of Sudbury.
"The art gallery […] is actually owned by Laurentian University and is subject of a sale by Laurentian University, so we don’t control what will happen with that building," said Wood, when asked what will happen to the locations that these three groups are currently in.
"The library belongs to the library board and I indicated to council this evening that the library board is considering selling that building and using the proceeds to assist with the construction of this new building. And then the multicultural centre would, although we’re working with them to find some way to remember that building in some fashion, but with them moving into Junction East, that building would be… would make way for the new building."
Those involved in the Junction East Project said it’s a way to revive the downtown core. This includes the Sudbury Theatre Centre, which isn’t inside the main building according to the latest plans but will still be a part of the community hub.
"We’re already on that site," said Patricia Meehan, the chair of the Sudbury Theatre Centre board.
"The new building is going to be our neighbor. We want to be part of this whole idea of participation and partnership and collaboration, was to look at how our organization and the partners could work together."
Meehan said the plan is to look at ways to collaborate between the new building and theatre, even if they aren’t physically joined. There was talk about a temporary structure or walkway to join the two buildings during the winter months. However, she said she would have liked to see the buildings attached permanently.
"It wouldn’t be honest to say that we weren’t disappointed, but that doesn’t mean that we don’t want to still partner and be part of this revitalization of our downtown and part of a community hub that we want to be proud of."
Tuesday's meeting presented the latest design, costs and specific details like accessibility features and operation plan. Although a few questions were voiced by councillors during the meeting, the support for the building was made evident.
"This is a remarkable and transformational project for the entire city, for all citizens and it will certainly be a project of great pride for Sudburians," said Mayor Brian Bigger. "What I heard tonight was a significant amount of support across our entire city council."
Also outlined was the current confirmed project funding of $12.3 million – around 13 per cent of the total estimated cost.
As of Tuesday evening, $800,000 has been confirmed through federal grants, $10 million in municipal funding and the Art Gallery of Sudbury has committed $1.5 million.
"We have developed a 10-year plan. We have put financing in place, anticipating significant investments in downtown and on behalf of all citizens across the entire city. We will manage the scope of the various downtown projects within the budgets that we have developed," said Bigger.
"One element that has always existed is an expectation of participant of funding from both the federal and provincial governments, and so I do believe that’s still part of our plan and so the expectation is that we will be able to move forward without significant increases in taxes. This project is absolutely affordable and it’s been planned well in advance."
CTVNews.ca Top Stories
Spectacular aurora light show to be seen across Canada Friday night
A rare and severe solar storm is expected to bring spectacular displays of the northern lights, also known as aurora borealis, across much of Canada and parts of the United States on Friday night.
Town of Fort Nelson, B.C., ordered to evacuate due to wildfire
The entire town of Fort Nelson, B.C., as well as the nearby Fort Nelson First Nation, has been ordered to evacuate due to an out-of-control wildfire.
Snowbirds in Vancouver for puck-drop flyby as Canucks face Oilers
The Canadian Forces Snowbirds will be performing a flyover across downtown Vancouver at the start of tonight's Stanley Cup playoff game between the Canucks and the Edmonton Oilers.
McGill University seeks emergency injunction to dismantle pro-Palestinian encampment
McGill University has filed a request for an injunction to have the pro-Palestinian encampment removed from its campus.
Which Canadian cities have the highest and lowest grocery prices?
Where you live plays a big factor in what you pay at the grocery store. And while it's no secret the same item may have a different price depending on the store, city or province, we wanted to see just how big the differences are, and why.
Swarm of 20,000 bees gather around woman’s car west of Toronto
A swarm of roughly 20,000 bees gathered around a woman’s car in the parking lot of Burlington Centre.
Video shows naked raccoon catching B.C. family by surprise
When Marvin Henschel spotted a strange and hairless creature wandering through a front lawn in B.C.'s Lower Mainland, he could barely believe his eyes.
Barron Trump declines to serve as an RNC delegate
Former U.S. President Donald Trump's youngest son, Barron Trump, has declined to serve as a delegate at this summer’s Republican National Convention, according to a senior Trump campaign adviser and a statement from Melania Trump's office.
Out-of-control wildfire prompts evacuation alert for Fort McMurray, Saprae Creek Estates Friday night
An evacuation alert was issued for two Wood Buffalo communities Friday night, as crews battled an out-of-control wildfire near Fort McMurray.